Preston Beach Recycling Scheme

Share Preston Beach Recycling Scheme on Facebook Share Preston Beach Recycling Scheme on Twitter Share Preston Beach Recycling Scheme on Linkedin Email Preston Beach Recycling Scheme link

Project Sign Off

The work to the beach finished on the 24th November, with the contractor and machinery then moving to Chiswell on Portland to commence further beach recycling and reprofiling as part of the area's Beach Management Plan.

The work moved around 11,000 cubic metres of shingle, meaning that a similar scheme of work should hopefully not need to be repeated for 5-10 years, depending on weather conditions and the rate of material loss through longshore drift.

Minor annual maintenance to cover the buried rock armour will resume when needed. The beach will not need to be closed for this.

The beach recycling and rock armour burial both ensure a high standard of protection given by the Preston beach defences, which includes the beach, seawall and promenade. The defences ensure a standard of protection with an annual probability of occurrence (APO) of 1% (1in 100 year return period) against overtopping and an APO of 0.2% (1 in 500 year return period) against breaching.



The Environment Agency (EA) delivered a beach recycling scheme on Preston Beach in Weymouth in early November 2025.

The operation started on Friday 7th November and lasted for just over 2 weeks ending on Monday 24th November. During the operation, machinery moved material from the North end of the beach, near Furzy Cliffs, back towards the Greenhill rock groyne end of the beach. This material had moved along the beach over time through a combination of coastal processes, such as longshore drift. The beach material was moved back to the South and central section of the beach to protect the underlying coastal defences and to improve the resilience of the defences against wave overtopping during the winter months.

While the works were ongoing, large areas of the beach and promenade had reduced access for public safety reasons. This included weekends. The public were asked to follow all signage and instructions from site staff. The work took place from the Greenhill rock groyne down to the beach that is in line with Bowleaze Cove car park. No beach recycling took place on Bowleaze Beach itself.

This webpage has been created to inform the local community, businesses and beach users about the operation and to answer any queries around the project delivery.

Follow the links below to find out more.






Project Sign Off

The work to the beach finished on the 24th November, with the contractor and machinery then moving to Chiswell on Portland to commence further beach recycling and reprofiling as part of the area's Beach Management Plan.

The work moved around 11,000 cubic metres of shingle, meaning that a similar scheme of work should hopefully not need to be repeated for 5-10 years, depending on weather conditions and the rate of material loss through longshore drift.

Minor annual maintenance to cover the buried rock armour will resume when needed. The beach will not need to be closed for this.

The beach recycling and rock armour burial both ensure a high standard of protection given by the Preston beach defences, which includes the beach, seawall and promenade. The defences ensure a standard of protection with an annual probability of occurrence (APO) of 1% (1in 100 year return period) against overtopping and an APO of 0.2% (1 in 500 year return period) against breaching.



The Environment Agency (EA) delivered a beach recycling scheme on Preston Beach in Weymouth in early November 2025.

The operation started on Friday 7th November and lasted for just over 2 weeks ending on Monday 24th November. During the operation, machinery moved material from the North end of the beach, near Furzy Cliffs, back towards the Greenhill rock groyne end of the beach. This material had moved along the beach over time through a combination of coastal processes, such as longshore drift. The beach material was moved back to the South and central section of the beach to protect the underlying coastal defences and to improve the resilience of the defences against wave overtopping during the winter months.

While the works were ongoing, large areas of the beach and promenade had reduced access for public safety reasons. This included weekends. The public were asked to follow all signage and instructions from site staff. The work took place from the Greenhill rock groyne down to the beach that is in line with Bowleaze Cove car park. No beach recycling took place on Bowleaze Beach itself.

This webpage has been created to inform the local community, businesses and beach users about the operation and to answer any queries around the project delivery.

Follow the links below to find out more.






Page last updated: 11 Dec 2025, 11:12 AM